Broad Street pavement failure after recent reconstruction
Fremont, California
Summary
The city is paying $39,123 over three years for LIDAR scans of every street, giving engineers a rating and damage map for each road. That means repair and resurfacing dollars can go where they're actually needed.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Last discussed May 12, 2026.
Impact analysis
The three-year contract costs $39,123.
Every driver in Fremont benefits from smarter street repair priorities.
Broad Street drivers are hitting potholes on a road that was just rebuilt with substantial public dollars.
Mentions & discussions (2)
City Council - Regular Meeting - May 12, 2026
Potholes are already appearing on Broad Street barely six months after it was repaved. Staff pulled core samples Friday to figure out whether the subgrade failed, possibly after extended water exposure during water main work, and the project is still open with money withheld from the contractor.
City Council - Regular Meeting - Jan 13, 2026
The city is paying $39,123 over three years for LIDAR scans of every street, giving engineers a rating and damage map for each road. That means repair and resurfacing dollars can go where they're actually needed.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Fremont, California
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.